Process and Expectations

At Waverley Bathrooms, our trades are full time employees, this allows us to run a fairly tight schedule. There is no waiting around for sub-contractors to become available dragging your renovation out for weeks or even months! Your site supervisor will update you along the way, with them being your point of contact you will always be up to date with the progress of the work.

Transparency in our process and customer expectations

Protection To Your Home

Trades people lay out drop sheets from door entry to job site for the protection of your floor coverings. Site clean up’s are also performed daily and on completion of your renovation.

There’s no place like home

Depending on the size of your renovation, there will be no need to stay elsewhere. Home services which include working toilet, gas, power and hot/cold water will always be available at the end of each working day for you and your family’s convenience.

Complete Renovation In Approximately 20 Working Days.

We always start and finish on time.

No Hidden Costs

Generous allowances made and you choose exactly what you want.

Supervision & Co-Ordination

Your renovation will be supervised and co-ordinated daily with communication being the key to your end result.

Bathroom Renovation Schedule

(Approximate Guideline Only)

Day 1-3:

  • Carpenter / Laborer, complete rip-out of bathroom
  • Carpenter / laborer, begin to re-construct new layout & material shopping.
  • Plumber, rough-in new plumbing points
  • Leave site clean & tidy.

Day 3-5:

  • Carpenter & plumber to continue.
  • Electrician, rough-in new wiring & install fan, ixl and lights if required.

Day 5-6:

  • Carpenter / Laborer, continue with construction, installation of wall linings, cabinetry & water-proofing.

Day 6-10:

  • Tiling begins after discussion with client.
  • Possible plasterer instead of tiler on this day.

Day 10-12:

  • Tiler continues if required.
  • Plasterer, stop-up, patch & cornice if tiler not required.
  • Shower screen measured (if custom made).

Day 12-13:

  • Tradesmen continue or finish off

Day 13-16:

  • Plumber, Fit-Off, Connect Tapware & Toilet, Fit Accessories, Seal All Internal Corners, Fit Shower Screen (If Packaged Type) & Clean Up
  • Labourer, Final Clean-Up, Removal Of All Builders Rubbish From Site

Complete!

Enjoy your brand new bathroom.

Need more information?

Licensed builders

We are licensed builders with HIA (House Industry Association) and HOW (Home Owners Warranty)

Further information is available upon request.

Our Trades

Most of our friendly staff are employed by us on a full time basis. We work closely with sub-contractors who we have built up trusting relationships with, ensuring quality of work which gives our clients peace of mind when doing work in your home.

Customize

We are able arrange items such as the shower screen and cabinetry to be custom built to your liking to maximize your bathrooms full potential.